Re: Utility Line Height


Beg to differ but the days of just putting it up are gone.  Most but  not all power companies will not let you violate the NESC. Further as I mentioned before sometimes the pole owner’s specifications exceed the NESC. We are waiting for the MRE on 2 projects that were suppose to be Q2 2021 but will be lucky if the pole owner grant permission by 2022.