Got an oddball job to bid. We're running hardline & drops to feed a Harbor there are about 300 slips fed 2 at a time from a fiberglass power & water pedestal then back under the dock to a lockbox with taps. We have to pull up one of the boards at each pedestal then feed the drops up through on all of them and about half are over water so we have to use a boat as well.
I got the hardline, lockboxes, splicing and design figured but have no idea what to bid for drops. We are all just lineman, splicers and directional bore guys and rarely deal with drops.
any help would be appreciated
Question for MDU guys
There are 7 replies to this message