Hi all, many thanks for the information shared. I have built on the east coast and we did not need the second loop. I have been trying to determine how to fix 200 tap locations. FYI we did a sample location of changing the tap bracket from 4" to 2 " and reclamed a bit of the construction loop, this may be acceptable to the client. One other option discussed is a extension connector? I just want to make sure what ever the finall call is I leave the client happy with our work.