Heads up ......

I know your looking at pricing right now, but let's not forget the all important factor of "Who" is gonna do that work.

10,000 traps in 30 days is about 334 traps a day. Figure 30 traps per man in a day average (figure some ladder climbs). That works about to an 11-man crew working 7-days a week.

IF you secure that 30-day contract for those 10,000 traps ... Do you have 11 guys committed and ready to go that are willing to hump it for 30-days straight with no days off?

If you have this ready to fire off "...diving into contracting" ... Then I say, "Good Luck Brodda-Man. Hope you GitRDone".

RadioMan