Along with the afore mentioned, make-ready may also have pole change outs, and down guy replacement, for broken guys and/or placement of anchors and guys where needed. A good make-ready person will also make note of dangerous poles (ie rotten butts,and broken tops etc.) for safety reasons.
> I am new to the cabling business, so can anyone please just give me a little info. on what make ready is, what do make ready crews do ? Thanks
Re: Make ready
Member #: 15330
Registered: 1996-2001
Posted:
45
Name:
Russell La Rue
Name:
Russell La Rue
Company:
Absolute Accuracy
Occupation:
Contract Mapper
Location:
Mid West
This is CABL.com posting #71911. Tiny Link: cabl.co/msR1
Posted in reply to: Make ready by Hawke2