> So your saying that if you leave an undg. LE (design - "LEM")in switch pos. #2 this is correct ? AT&T required us to re-visit every "LEM" location and move the switch position from #2 - #1.
>
> > As far as the switch is concerned.....Position 1 = Thermal set-up.....Position 2 = manual set-up......and position 3 = agc setup.
> >
> > The part number for this manual is 593161 Rev D...www.scientificatlanta.com
> >
> > >

> > >
> > > I am a new (sweep) qc tech. (4 yrs. as Maint. Tech so not a newbie) I have 2 questions, thanks for your help.
> > >
> > > Question: 1
> > >
> > > What is the correct switch setting (1 or 2 -no agc)and IS pad and eq for an LE designed as a "LEM" - undg.?
> > >
> > > Question: 2
> > >
> > > Where is my best resourse for "application notes" for additional simular questions concerning sweep procedures ?.
> > >
> > > I prefer online access, as I need to educate myself quickly.
> > >
> > >
> > > Thank you again for your help.
> > >
> > >