i am trying to change these lock boxes out here in atlanta in these mdu's. when i took the job everyone is telling me you can do 10 per man per day. i have tried it with a three man indipendent crew and with a six man buddy crew. i can not get over 4 per day with all the fabrication one has to do in the field. nobody told me about all the splicing and extentions one has to do. i know i am working for crazy specs but i have some men that have been with me for a while and i am trying to keep a check coming too. has anybody else seen this same let me know if i am beating a dead horse so i can stop racking my brain please. any help or one with more knowledge i would like to here from.