Re:need local splicers for mdu ped replacement in atlanta
>mostly 1290's and 1310's . average 10 1290's per/day/man
>5 1310's per/day/man... contact ed @ 770-483-3789
> (-REDACTED-)
>
>
>
>Exhibit A Composite Pricing Detail
>1290 MDU Audit Security-Replace any single/dual tap pedestal with a high security
>
>pedestal up to a 12"X12"X36" $ 25.00
>This includes the following items:
>1. Wreck-out and removal of old pedestal and proper disposal
>2. Installation of anti pullback stack(s)
>3. Extending drops up to 10'
>4. Mount all components to brackets
>5. Comply to all composite type requirements
>
>
>1300 MDU Audit Security- install 1 bag quick set cement (concrete) up to a 12"X12"X36"
>pedestal base $6.00
>This includes the following items
>1. Install 3 spare- 2" flex conduits/approx. 30"!ong-capped at both ends (no foam fillers)
>2. Extend all conduits and wiring with split flex duct and capped ends
>3. The vendor will supply the 60-lb. bag of quick cure cement and any necessary
>water
>
>1310 MDU Audit Security-pedestal installation up to a 12"X12"X36" Ped to box $42.00
>
>Cat/doghouse style ped
>
>This includes the following items:
>1. Splice up to a combination of 4 passives taps/splitters
>2. Splice and connect to adjacent amp "cat house" pedestal
>3. Installation of anti pull back stake
>4. Extend drops up to 10'
>5. Transfer/dress and connect all active drops
>6. Install/dress all filters and terminators
>7. Wreck-out/dispose ped & restoration
>
>8. Comply with all composite type requirements
>
>
>1320 MDU Audit Security-composite damage replacement of upgraded lockbox at same
>location $25.75
>This includes the following items:
>1. Remove and dispose of damaged lockboxes
>2. Mount/transfer all drop components and ground/bond
>3. Fix or replace lockbox conduits up to 10'
>1330 MDU Audit Security-composite replacement of damaged lockbox to new location
>up to 10' (converting old style to new) $65.00
>This includes the following items:
>1. All items included with 1080 composite
>1340 MDU Audit Security-composite conversion from pedestal to lockbox-must be
>Within 5' of building. Underground covered by existing composite. $65.00
>This includes the following items:
>1 All items included with 1080 composite
>2. Removal of pedestal/restoration
>1350 MDU Audit Security-composite repair of diversified lockbox $8.00
>This includes the following items:
>1. Secure lockbox to wall
>2. Replace/fix cover, hinge or any internal panel
>you know you sit hear running this ad over and over...hello your prices SUCK!!!!!you need MDU WORK but you don't want to pay for it..you think a splicer is going to spend 2-3 hours on a LOCKBOX not a ped for the chump change you offer,,you are a insult to the industry and probably shouldn't hold a contract but on ther other hand you may find some idiots out there that don't know what there doing,but like all people you think you will profit more stop trying to fatten the pocket..what ever happened to honest days labor for honest pay...you need to stop posting this same ad and go change your own lockboxes and splicing for pocket full of beans.high security at that so that means your truck will probably be broken into!!!!!!anyway if you come to terms and want to pay for good work we can talk about a composite price per unit!!!!other than that you don't need splicers so stop posting that you do it should say idiots inquire within!~!!!
>
>
>
This is CABL.com posting #46464. Tiny Link: cabl.co/mmfA
There is 1 reply to this message