I always put a cap on retention, something like $5000. I felt if anything was wrong that the sub did exceeded $5K, then it was my fault for keeping him on site. Also I always told my subs to keep a running total of retention held at the bottom of their weekly re-cap on billing. I once open an account on each sub for the retention held on big jobs which was agreeable by both parties. At the end of year or tax time I would release all of it. Usually on big projects, after 90 days I quit holding retention, by then you knew the sub was working with you and did good quality work. It works for both parties. Keep Safe:Microman