Let me put it this way; 1500’/5 days = 300’/day. That would be only 2 pole spans per day. Just recently 2 old guys (mid 60s) stranded, lashed fiber and wrecked out the old figure 8 bundle of 4 strands/fibers in 1 short day in December. So that’s a total of 1500’ in one day. Like others have said 5000’/ day is the goal. So 15000’ / week is more like it. 