Re: Aerial cable leasing and overlashing


You didn’t mention 2 of the most important obstacles, Street side/alley vs easement and how bad are the trees. It also depends on number of; 90s, underground dips, places to figure 8, mid span bugnuts, mid span drops, fences, mean dogs, mean people, stupid people, warehouse location and traffic/traffic control. 

That at said a good 3 man crew could finish as little as 1200 to 5000 feet a day. I know this is a big window but it is as close as I can give you with the info I have. 
This is CABL.com posting #375246. Tiny Link: cabl.co/mbJMw
Posted in reply to: Aerial cable leasing and overlashing by Dave1818
There are 3 replies to this message
Re: Aerial cable leasing and overlashing Dave1818 1/19/2018 8:50:47 PM
Re: Aerial cable leasing and overlashing danimal 1/13/2018 5:07:10 AM
Re: Aerial cable leasing and overlashing skidmark167 1/12/2018 9:14:01 PM