That is an accurate statement.
Poles loading is measurements of all conductors primary on down, angles of conductors, wire sizes, etc. and takes much more time per pole to complete compared to a make ready survey which is typically measuring lowest power conductor down thru all the communications cables.
Take Care
Chris Kramer