won't work for pipe footage. 10000 foot reel if you start in the middle you have to pull 5000 foot for 800 to 1000 foot of pipe and if they want 100 foot of storage you have to handle the first valt once for free . the second valt twice ,third three times, pulling and figure eighting.So if they want 10000 foot of fiber in 8000 to 9000 foot of pipe they should pay for 10000 foot of fiber.Contractors that place composite pipe and fiber only get pipe footage so don't want to pay tail to tail.
Re: Pipe footage vs sheath footage
There is 1 reply to this message