Re: aerial fiber


Got a dollar a ft. in Colo. in 07..that's the last job I did..don't know the prices today. Just for the hell of it I attached the prices on everything....I'm out of it now but these were the Prime prices I bid and got at that time.. Paid the subs 60% off this price sheet. 

                    Colorado Price Schedule…ending 12, 2007.

 

       Aerial      Place aerial new build (2 cables)              1.00 ft.

                   Replace coax (1 cable)                           1.00 ft.

                   Each additional cable                              0.35 ft.

                   W/O old coax when replacing new             0.32 ft.

                   W/O aerial separate trip                           0.18 ft.

                    Reframe straight through pole                        40.00 ea.

                    Reframe dead end pole                                 50.00 ea.

                    Reframe junction pole                                   50.00 ea.

                    Place down guy                                           25.00 ea.

                    Place screw anchor                                      45.00 ea.

                    Install anchor in concrete                              75.00 ea.

                    Install VGR                                                  27.00 ea.

                    Install extension arm                                     15.00 ea.

                    Install sidewalk guy arm                                 15.00 ea.

                    Install rock anchor                                        95.00 ea.

                    Delash & relash fiber to existing cable        1.00 ft.

                    Delash & relash broken lashing wire           1.00 ft.

                    Attach self support to bldg.                     1.20 ft.

                    Install aerial strand                                 0.49 ft.

                    Tree trimming                                         0.17 ft.

       Fiber Spl.    1-12                                                      33.25 ea.

                       13-48                                                     33.25 ea.                                                   

                       49-72                                                      33.25 ea.

                       73-144                                                     33.25 ea.  

                       145-216                                                    33.25 ea.

                       217-188                                                    33.25 ea.

                        

                       289 and above                                            33.25 ea.

                       Hourly

                       2 man crew (OT)                        100.00 hr.

                       3 man crew (OT)                         50.00 hr.

                       2 man crew (regular hours)             90.00 hr.

                       3 man crew (regular hours)            120.00 hr.

                       Backhoe (OT)                                92.50 hr.

                       Backhoe regular time                       75.00 hr.

                       Supervisor                                      50.00 hr.

                       Supervisor (OT)                               65.00 hr.

                       Fiber splicer                                     80.00 hr.

                       Fiber splicer (OT)                             120.00 hr.

                       Splicer                                              45.00 hr.  

                       Splicer (OT)                                        67.50 hr.

                       Warehouse man                                    45.00 hr.

                       Warehouse man (OT)                             67.50 hr. 

Joint trench        One 2” CIC                                                1.20 ft.

                        Each additional 2” CIC                                  0.20 ft.

                        One 4” conduit                                            0.85 ft.

                        Each additional 4” conduit                              0.25 ft.

                        Install vault                                      75.00 ea.

                        Place drop duct from tap to home         150.00 ea.

MDU:                 Pre-wire                                            30.00 drop

                        Post-wire                                           40.00 drop

                        Pre-wire with molding                            40.00 drop           

                        Post wire with molding                           50.00 drop

                        Post wire re-work                                 15.00 drop

                        Post wire wreck out                                6.00 drop

                        Wall fish                                           35.00 ea. 

                        Install wall plate                                  2.00 ea.

                        TV jumper                                           2.00 ea.

                        Cut tag and ohm drop                            2.50 ea.

                        Pre-wire inside unit                                  14.00 drop

                        Pre-wire home run                                    20.00 drop

                        Pre-wire additional home run                      17.00  drop

                        Trim                                                   2.00 ea.

                        Trap drop                                            2.00 ea.

                        Core drill                                           125.00 ea.

                        Install molding                                              0.75 ft.

                        Wreck out molding                                         0.15 ft.

                        Bury drop, min. 6” in conduit                 150.00 ea.

                        Drop extension                                       2.00 ea.

                        Post wire re-work                                    5.00 ea.

                        X-Ray floors                                             Cost +  

                        Place 1” EMT with materials                 11.50 ft.

         Joint Laterials:Joint trenching                              56.00 ft.

                        Additional footage                                0.56 ft.   

                        OPE installation                                         10.00 ea.

          Place fiber: Lash first aerial fiber cable                    1.00 ft.

                  

                         Lash additional fiber cable                       0.42 ft.

                         Delash relash when chasing slack              0.95 ft.

                         Place fiber in open duct                           1.00 ft.

                         Place fiber in occupied duct                      1.00 ft.

                         Install snow shoe                                        15.00 ea.

                         Place fiber enclosure                                   250.00 ea.    

                         Re-enter enclosure                                      185.00 ea.

                         Optimize node                                             125.00 ea.

      Power supply: Install PS aerial                                          1280.00 ea.

                            

                         Install PS underground                                 1380.00 ea. 

                         Wreck out PS aerial                                      125.00 ea

                         Wreck out PS UG                                          125.00 ea.

                         Change out module                                         75.00 ea.

     Splice/Activate Splice UG plant output footage                 0.45 ft.

                          Activate UG plant output footage              0.08 ft.

                          Splice aerial plant output footage              0.45 ft.

                          Activate aerial plant output footage           0.08 ft.

     Sweep & cert.   Sweep & certify plant                             0.28 ft.

                           

     Underground:   Dir. Bore set up less than 100’                      250.00 ea.

                          New build 24” Tr.                                   10.50 ft.

                          New build 30” Tr.                                   11.00 ft.

                          New build 36” Tr.                                   11.50 ft.

                          New build 48” Tr.                                   14.00 ft.

                          Maint. 24” Tr.                                        12.50 ft.

                          Maint. 30” Tr.                                        13.00 ft.

                          Maint. 36” Tr.                                         13.50 ft.

                          Maint. 48” Tr.                                         15.00 ft.

                          Abnormal soil adder                                   3.00 ft.

                          ROW haul material                                        18.00 ton

                          Haul road base, spread, repack                         Cost +

                          Dig up expose conduit 24”                             175.00 ea.

                          Rod and rope existing duct                          0.40 ft.

                          Install tap ped.                                              18.00 ea.

                          Install splitter ped.                                         22.00 ea.

                          Install LE/Amp Ped.                                         60.00 ea.

                          Install large vault                                          200.00 ea.

                  

                          Install manhole 4x4x4                                     650.00 ea.

                          Direct. Bore up to 2-2” conduits                17.00 ft.

                          Direct. Bore each additional 2”                    0.20 ft.

                          Direct. Bore 1-4” steel pipe with material     30.00 ft.

                          Direct. Bore add. 4” steel pipe                    15.00 ft. 

                          Direct. Bore 1-2” steel with material            26.50 ft.

                          Direct. Bore additional 2” steel                     0.40 ft.

                          Vacuum Pothole hard surface                          200.00 ea.

                          Pothole, locate, hard surface                           150.00 ea.

                          Pothole hard surface/infrared                           500.00 ea.

                          Pull maxcell                                                0.35 ft. 

                          Repair conduit                                               45.00 ea.

                          Remove vault                                               150.00 ea.  

                          Place up to 2 coax ca. in occupied conduit        1.25 ft.

                          Place up to 2 coax ca. in clear duct                 1.10 ft.

                          R&R asphalt                                                18.00 sf.

                          R&R concrete                                              22.00 sf.

                          Engineer drawings for permit                               cost +    

                          Install riser                                                    80.00 ea.

                          Standard 2” core drill                                     125.00 ea.

                          Flow fill                                                           Cost +

                          Permit coordinator                                         Cost + trip

                          Asphalt R&R Minimum charge                          525.00 Loc.

                          Concrete R&R Minimum charge                        735.00 Loc.

 

 

                            

 

 

 

 

      

                        

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

This is CABL.com posting #277267. Tiny Link: cabl.co/mbkid
Posted in reply to: Re: aerial fiber by cantgetright
There is 1 reply to this message
Re: aerial fiber cantgetright 10/27/2009 4:56:12 PM