Create your free account now! Sign up

Re: Linemen-What's Your Favorite Work Relateted Me


Come on feeber, first it was 130' poles now its nearly five miles of fiber drive off in eight hours (if you started at 6:30 a.m.) lets say the spans were 300' (good running) 24000 div.by 300= 80 poles div. by 8 hrs= 10 poles every hr.= 6 minutes per pole to lash, swap lasher, bond pole, drive to next pole, put in storage loops,etc.etc......and they were prolly 130' poles on top of that, you my man are one badass lineman if this is true...
This is CABL.com posting #253709. Tiny Link: cabl.co/mbeaf
There are 5 replies to this message