i'D BUDGET 20 WORK DAYS TAKING WEATHER, EASEMENT, TREES AND TO BE ON SAFE SIDE 30 WORK DAYS. IF ANCHORING,GUYING ANOTHER 5 DAYS. NOW IF YOU WANT MY CREWS TO COME AND GET R DONE---10 DAYS WITH ANCHORS-BONDS-VGR-PG-OHG. ADD 3 FOR 5/16 ADD 5 FOR 3/8 STRAND. iF POWER POLES THEY SHOULD BE USING ADSS FIBER
GOOD LUCK-KEEP IT SAFE.