Create your free account now! Sign up

Re: Underground Splicing rates


depends a WHOLE bunch on the work. I have worked from .05/ft to .65/ft, made and lost money with both.

We need a LOT more info, then we can let you know if it is good or not. Give me the average spans, are you billing trench or cable footage, is it new build, retro or over build, how much stuff is easement, what kind of gear are you using, how much work will they be able to give you (if you only can get 1000 ft a day, then you can only make 100 bucks a day) etc., etc...

Right now, I would say most likely not.


Vic
you need to have enough wisdom to keep from making the wrong decisions but enough courage to make the right ones
This is CABL.com posting #151128. Tiny Link: cabl.co/mNtI
Posted in reply to: Underground Splicing rates by CoalStove1974
There is 1 reply to this message
Re: Underground Splicing rates Victor 8/17/2005 3:52:00 PM