The first reply was right, always have some one watch the trailer and the pile. When pulling, make sure that you aren't pulling across any straps or sharp objects. A strap can skin the jacket like you wouldn't believe, right down to the armor or buffer tubes.
As far as production - day in/ day out if you average 3,500-4,500 a day of completed fiber you're doing decent. You can get on runs that you can get a lot more but, trees, 90's and slacks will slow you down.